The New Ferry Is Progressing Nicely In our last newsletter we showed you pictures of the aluminum pilot houses being welded, fitted and painted at Nichols boatyard.
These new pictures show you the pilot house being lifted by a crane and placed into position on top of the other welded aluminum sections.
Nichols Brothers is completing the three “grand modules” that make up the Ferry and the three completed chunks will be barged down to Todd Pacific shipyards in January where they will be set on the steel hull of the Ferry and welded into place.
Todd Pacific Shipyards is building the steel hull of the new ferry and will be assembling the aluminum sections and attaching them to complete the whole Ferry puzzle.
|